Solar farm

Solarpark Bernburg solar farm

Solarpark Bernburg solar farm is a solar farm in Germany with a capacity of 4.2 MW, commissioned in 2022. It is operating and is owned by Besst Zwei GmbH.

In 2024 it settled 1.6 GWh of electricity, a load factor of 4.5%. Part of that volume was sold outside EEG support, so it is partly merchant.

Its EEG support runs to the end of 2042, after which that output is sold at market prices.

Measured performance vs peers
4.5%
This assetCohort median 9.7%Middle half

This asset produced at 4.5% of nameplate in 2024 — the 9th percentile of German solar commissioned 2020 or later (1,271 assets with metered output).

Capacity
4.2 MW
Country
Germany
Status
operating
Commissioned
2022
Owner
Besst Zwei GmbH
Technology
PV
Measured output 2024
1.6 GWh
Load factor
4.5%
EEG support ends
2042
Peer percentile
9th
Grid connection
MS
State
Sachsen-Anhalt

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE980830811406); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets

←CapexAtlas|ScreenerMap