Solar farm

Solarpark Salmünster 1 (2.Teil) solar farm

Solarpark Salmünster 1 (2.Teil) solar farm is a solar farm in Germany with a capacity of 5.9 MW, commissioned in 2022. It is operating and is owned by next energy projects 2050 GmbH.

In 2024 it settled 327 MWh of electricity, a load factor of 0.6%. It sold essentially all of that volume outside EEG support — it is already merchant.

Measured performance vs peers
0.6%
This assetCohort median 9.7%Middle half

This asset produced at 0.6% of nameplate in 2024 — the 2nd percentile of German solar commissioned 2020 or later (1,271 assets with metered output).

Capacity
5.9 MW
Country
Germany
Status
operating
Commissioned
2022
Owner
next energy projects 2050 GmbH
Technology
PV
Measured output 2024
327 MWh
Load factor
0.6%
Peer percentile
2nd
Grid connection
MS
State
Hessen

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE917056239851); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets