Solar farm

SP 1/1 Eigenbetrieb Gemeinde Lübesse solar farm

SP 1/1 Eigenbetrieb Gemeinde Lübesse solar farm is a solar farm in Germany with a capacity of 1.5 MW, commissioned in 2011. It is operating and is owned by Amt Ludwigslust-Land, Wöbbeliner Straße 5, 19288 Ludwigslust.

In 2024 it settled 1.5 GWh of electricity, a load factor of 11.3%. That volume was settled under EEG support.

Its EEG support runs to the end of 2031, after which that output is sold at market prices.

Measured performance vs peers
11.3%
This assetCohort median 10.5%Middle half

This asset produced at 11.3% of nameplate in 2024 — the 77th percentile of German solar commissioned 2010-2014 (2,063 assets with metered output).

Capacity
1.5 MW
Country
Germany
Status
operating
Commissioned
2011
Owner
Amt Ludwigslust-Land, Wöbbeliner Straße 5, 19288 Ludwigslust
Technology
PV
Measured output 2024
1.5 GWh
Load factor
11.3%
EEG support ends
2031
Peer percentile
77th
Grid connection
MS
State
Mecklenburg-Vorpommern

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE929038630792); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets

←CapexAtlas|ScreenerMap