Wind farm

Hof (Trasse Münchberg) wind farm

Hof (Trasse Münchberg) wind farm is a wind farm in Germany with a capacity of 18 MW, commissioned in 2012. It is operating and is owned by Lacuna Windpark Hohenzellig GmbH & Co KG.

In 2024 it settled 22.9 GWh of electricity, a load factor of 14.5%. That volume was settled under EEG support. This figure is apportioned across units of the same site that share a registry entry.

Its EEG support runs to the end of 2035, after which that output is sold at market prices.

Measured performance vs peers
14.5%
This assetCohort median 21.9%Middle half

This asset produced at 14.5% of nameplate in 2024 — the 3rd percentile of German wind commissioned 2010-2014 (128 assets with metered output). Its volume is apportioned across phases sharing one registry entry, so treat the figure as an estimate for this unit and exact for the site.

Capacity
18 MW
Country
Germany
Status
operating
Commissioned
2012
Owner
Lacuna Windpark Hohenzellig GmbH & Co KG
Technology
Onshore
Measured output 2024
22.9 GWh
Load factor
14.5%
EEG support ends
2035
Peer percentile
3rd
Grid connection
HS/MS
State
Bayern

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE922754526226); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets