Wind farm

Behrendorf wind farm

Behrendorf wind farm is a wind farm in Germany with a capacity of 19 MW, commissioned in 2015. It is operating and is owned by 2. Bürgerwindpark Behrendorf GmbH & Co. KG.

In 2024 it settled 27.1 GWh of electricity, a load factor of 16.3%. That volume was settled under EEG support. This figure is apportioned across units of the same site that share a registry entry.

Its EEG support runs to the end of 2032, with later phases to 2037, after which that output is sold at market prices.

Measured performance vs peers
16.3%
This assetCohort median 24.7%Middle half

This asset produced at 16.3% of nameplate in 2024 — the 7th percentile of German wind commissioned 2015-2019 (215 assets with metered output). Its volume is apportioned across phases sharing one registry entry, so treat the figure as an estimate for this unit and exact for the site.

Capacity
19 MW
Country
Germany
Status
operating
Commissioned
2015
Owner
2. Bürgerwindpark Behrendorf GmbH & Co. KG
Technology
Onshore
Measured output 2024
27.1 GWh
Load factor
16.3%
EEG support ends
2032
Peer percentile
7th
Grid connection
MS
State
Schleswig-Holstein

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE924884877261); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets