Wind farm

Druiberg wind farm

Druiberg wind farm is a wind farm in Germany with a capacity of 14 MW, commissioned in 2004. It is operating and is owned by GeneralRenawables GmbH & Co. KG.

In 2024 it settled 24.3 GWh of electricity, a load factor of 19.8%. That volume was settled under EEG support.

Its EEG support ran to the end of 2024.

Measured performance vs peers
19.8%
This assetCohort median 16.3%Middle half

This asset produced at 19.8% of nameplate in 2024 — the 74th percentile of German wind commissioned pre-2010 (182 assets with metered output).

Capacity
14 MW
Country
Germany
Status
operating
Commissioned
2004
Owner
GeneralRenawables GmbH & Co. KG
Technology
Onshore
Measured output 2024
24.3 GWh
Load factor
19.8%
EEG support ends
2024
Peer percentile
74th
Grid connection
HS
State
Sachsen-Anhalt

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE918484123262); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets