Solar farm

NOR FLAGBALG solar project

NOR FLAGBALG solar project is a solar farm in Germany with a capacity of 1.1 MW, commissioned in 2023. It is operating and is owned by AVL Verwaltung und Leasing GmbH & Co. KG.

In 2024 it settled 407 MWh of electricity, a load factor of 4.2%. It sold essentially all of that volume outside EEG support — it is already merchant.

Measured performance vs peers
4.2%
This assetCohort median 9.7%Middle half

This asset produced at 4.2% of nameplate in 2024 — the 9th percentile of German solar commissioned 2020 or later (1,271 assets with metered output).

Capacity
1.1 MW
Country
Germany
Status
operating
Commissioned
2023
Owner
AVL Verwaltung und Leasing GmbH & Co. KG
Technology
PV
Measured output 2024
407 MWh
Load factor
4.2%
Peer percentile
9th
Grid connection
NS
State
Niedersachsen

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE946281118693); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets