Solar farm

PVA Hennickendorf 3 BNA solar project

PVA Hennickendorf 3 BNA solar project is a solar farm in Germany with a capacity of 1.3 MW, commissioned in 2023. It is operating and is owned by ST Solarinvestitionsgesellschaft Sachsen-Anhalt 1 mbH.

In 2024 it settled 483 MWh of electricity, a load factor of 4.2%. That volume was settled under EEG support.

Measured performance vs peers
4.2%
This assetCohort median 9.7%Middle half

This asset produced at 4.2% of nameplate in 2024 — the 9th percentile of German solar commissioned 2020 or later (1,271 assets with metered output).

Capacity
1.3 MW
Country
Germany
Status
operating
Commissioned
2023
Owner
ST Solarinvestitionsgesellschaft Sachsen-Anhalt 1 mbH
Technology
PV
Measured output 2024
483 MWh
Load factor
4.2%
Peer percentile
9th

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE998704383072); commissioning date and grid connection from EEG-Anlagenstammdaten. All Germany assets