Solar farm

QWB COE Floating PV solar project

QWB COE Floating PV solar project is a solar farm in Germany with a capacity of 2.8 MW, commissioned in 2024. It is operating and is owned by Quarzwerk Baums GmbH & Co. KG.

Its EEG support runs to the end of 2044, after which that output is sold at market prices.

Capacity
2.8 MW
Country
Germany
Status
operating
Commissioned
2024
Owner
Quarzwerk Baums GmbH & Co. KG
Technology
PV
EEG support ends
2044
Grid connection
MS
State
Nordrhein-Westfalen

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); ownership established by research against marktstammdatenregister.de (SEE939972865440); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets