PVPark Kirrweiler TR01 solar project is a solar farm in Germany with a capacity of 3.9 MW, commissioned in 2024. It is operating and is owned by Windpark Kirrweiler GmbH & Co. KG.

In 2024 it settled 1.5 GWh of electricity, a load factor of 4.5%. That volume was settled under EEG support. This figure is apportioned across units of the same site that share a registry entry.

Its EEG support runs to the end of 2044, after which that output is sold at market prices.

Peer comparison unavailable

Commissioned 2024, settled 2024 — a partial year of output over a full year of nameplate. Not comparable.

Capacity
3.9 MW
Country
Germany
Status
operating
Commissioned
2024
Owner
Windpark Kirrweiler GmbH & Co. KG
Technology
PV
Measured output 2024
1.5 GWh
Load factor
4.5%
EEG support ends
2044
Grid connection
MS
State
Rheinland-Pfalz

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE954277966043); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets