Solar farm

FREILAND BREITENMOOS WINDACH 2b solar project

FREILAND BREITENMOOS WINDACH 2b solar project is a solar farm in Germany with a capacity of 1 MW, commissioned in 2022. It is operating and is owned by Gemeindewerke Windach.

In 2024 it settled 1.5 GWh of electricity, a load factor of 17.5%. That volume was settled under EEG support.

Its EEG support runs to the end of 2042, after which that output is sold at market prices.

Measured performance vs peers
17.5%
This assetCohort median 9.7%Middle half

This asset produced at 17.5% of nameplate in 2024 — the 100th percentile of German solar commissioned 2020 or later (1,271 assets with metered output).

Capacity
1 MW
Country
Germany
Status
operating
Commissioned
2022
Owner
Gemeindewerke Windach
Technology
PV
Measured output 2024
1.5 GWh
Load factor
17.5%
EEG support ends
2042
Peer percentile
100th
Grid connection
MS
State
Bayern

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE927103983545); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets