Solar farm

Solarpark Traufwiesen solar project

Solarpark Traufwiesen solar project is a solar farm in Germany with a capacity of 8.7 MW, commissioned in 2024. It is operating and is owned by Solarpark Traufwiesen GmbH & Co. KG.

In 2024 it settled 5.5 GWh of electricity, a load factor of 7.2%. It sold essentially all of that volume outside EEG support — it is already merchant.

Peer comparison unavailable

Commissioned 2024, settled 2024 — a partial year of output over a full year of nameplate. Not comparable.

Capacity
8.7 MW
Country
Germany
Status
operating
Commissioned
2024
Owner
Solarpark Traufwiesen GmbH & Co. KG
Technology
PV
Measured output 2024
5.5 GWh
Load factor
7.2%
Grid connection
MS
State
Baden-Württemberg

Sources: asset record from Global Energy Monitor; ownership from the Marktstammdatenregister (DL-DE-BY-2.0); output and subsidy status measured from EEG settlement data for 2024, not modelled; ownership established by research against marktstammdatenregister.de (SEE940496491251); commissioning date and grid connection from EEG-Anlagenstammdaten, with the support end year derived from the EEG’s 20-year tenor. All Germany assets